摘要:本毕业设计为重庆科技学院经济适用房C4栋投标文件编制。工程所在地为重庆沙坪坝区虎溪镇大学城。该工程的建设单位为重庆科技学院,由重庆大学建筑设计研究院设计,施工图纸齐全。采用人工挖孔桩基础,上部主体为剪力墙结构,结构安全等级为二级,建筑耐火等级一级,抗震设防烈度为六度,工程类别一类,居住户数307户,总建筑面积18747.84平方米。
该投标文件的编制是以重庆科技学院经济适用房C4栋施工设计图纸,国家和地方现行的一系列施工和技术规范、标准等为依据,套取“重庆市建筑工程计价定额(2008)”,取费标准按照一类工程计取,材料价差按照2013年4月份市场信息计取。
在毕业设计编制过程中,使用广联达图形软件和钢筋算量软件,结合手工算量,完成工程量计算,然后应用广联达计价软件进行套价,最终得出该工程的工程造价为17,124,355.86元。这个过程中,由于软件操作的生疏,对定额规范的不熟悉,出现了错项、漏项的情况;不过,这些问题在老师的指导和同学的帮助下最后都一一解决了。
通过这次毕业设计,我的业务水平提升了一定层次,主要有以下几点收获:一是学习了一栋住宅从头至尾的预算内容;二是软件操作技巧有所巩固和提高;三是对于手工算量的计量规则更加明确了。
关键词:工程概况 编制依据 困难 解决方法
ABSTRACT:This graduation design for the Chongqing University of Science and Technology affordable housing building C4 the preparation of tender documents, The project is located in Huxi town Chongqing city Shapingba District University. The project construction units for the Chongqing University of Science and Technology, architectural design by the Institute of Chongqing University, and construction drawings complete. The artificial hole digging pile foundation, the upper part of the main for the concrete structure, the structural safety of grade II, the fire resistance of grade I, for the six seismic fortification intensity, type of construction work for the one category. It can accommodate 307 households. The total construction area of 18747.84 square meters.
The preparation of the bidding documents is the Chongqing University of Science and Technology affordable housing C4 building construction design drawings, national and local construction and the existing series of technical specifications, standards-based, Taking "valuation norm of Chongqing Construction Engineering (2008)," fee standards according to the type of construction work for the one category. The material price of difference calculation is taken the market information in 2013 April.
In the process of graduation design, using the software of GuangLianda drawing calculation and steel calculation, combined with manual calculation completed of the project and apply valuation software to take the price, finally the engineering cost of the project is RMB 17124355.86. In this process, because the software operation of the strange, unfamiliar with the quota standard, appeared in the wrong item, leak case; however, these problems are solved by teacher's guidance and students’ help.
Through this graduation design, my business level in a certain level, mainly has the following several points: one is the harvest of learning a house budget content from a to z; two is to consolidate and improve the software operation skills; three is to gauge manual calculation is more clear.
Keywords: Project Introduction; Code and Standard; Difficulties; Method.